Walking History Tour Markers Update
Walking History Tour Markers Update

- Members of HPAC are assisting with fact-checking marker content. Photos are gathered and waiting for sources to be finalized. Information will be mailed to Museum in the Streets with finished copy to begin marker fabrication.
- We are working with Catalyst Signworks for marker installation. They have provided their formal proposal. The board has voted in favor of providing the deposit to begin the preliminary scope, which the entirety of the project scope is outlined below:
LARGER PANELS
– 8” from grade to bottom of each sign where applicable (panels are to be 47”x64”)
– Aluminum grid backer panel (per provided hand drawings – these will be reinterpreted digitally by Catalyst) o Qty (2) posts, welded to grid backer panel and with pre-drilled holes per provided specs via MITS.
– Satin black finishing on fabricated hardware.
SMALLER PANELS
– 51” from grade to the bottom of each sign panel (20”square plate)
– Aluminum backer panel (per provided hand drawings – these will be reimagined digitally by Catalyst) o Qty (12) posts, welded to grid backer panel and with pre-drilled holes per provided specs via MITS.
– Satin black finishing
• Site labor dig and stage footings
– Site conditions across 14 locations TBD and may affect costing once realized & Provide all footing and installation materials as required (tbc post-survey)
• Call for township footing inspection at each location and receive approvals
– Accounting for technician onsite for (1) day and to be scheduled accordingly. & Additional time, if required for coordination, will be additional in cost.
• Pour footings:
– with concrete materials, let posts cure, then return to install marker panels.
• Final Inspections:
– Meet inspector for each site final inspection (1 day onsite allocated in budget) & Receive and document final paperwork
• Provide labeled and organized completion photos to client